Data center, 80 units of 2,100 kW
- Scope
- about 168 MW of backup capacity; design, supply, installation and commissioning
- Result
- largest data center project of the partner plant
Solution
Grid connection takes months or years, but the site has to start now. Containerized gensets and storage power construction and the first phase, and after grid connection they become its backup.
Key figures
up to 100 MW
supplied within 4 months depending on project location
manufacturer data3 months
for a 2.5 MW containerized data center unit
manufacturer data0
redundant equipment: after grid connection the units move to backup duty
OS Power schemeCapacity at the right point of the grid becomes available in a year or later.
Cranes, concrete, welding and site cabins need power from day one.
A data center, plant or camp wants to start operating before the substation is commissioned.
Solution
A power module of containerized gensets and storage: primary source first, backup after grid connection.
After grid connection the gensets move to backup duty without replacing equipment.
| Stage | Equipment | Role of generation |
|---|---|---|
| Construction | trailer-mounted units | primary source |
| First phase | containerized power module and storage | primary source |
| After connection | the same units | backup, test runs |
Lead times depend on power rating, design and plant workload; they are confirmed in the commercial proposal.
See also: Connection without grid upgrade
Manufacturer data. Details and references on request after approval by customers.
1-3 MVA units with data center rating, containerized power modules and fuel for 48-72 hours.
Learn more48 V DC gensets and solar hybrids: 40-60 % fuel savings.
Learn moreContainerized units and hybrid with storage: less fuel, fewer deliveries and engine hours.
Learn more100-3,000 kVA units, ATS, parallel operation and synchronization.
Learn moreThe genset runs less often and at efficient load: less fuel, fewer engine hours and site visits.
Learn moreRequest
Load and load profile, operating mode (backup or primary source), climate, grid availability, noise and fuel requirements. We will reply with a configuration, lead time and proposal.