Illustration: an OS Power containerized storage unit next to the distribution substation of a new site

Solution

Connecting a site without waiting for grid upgrades

In constrained grid nodes, a capacity increase takes years. The storage charges within the allocated capacity and covers peaks above it, so the site can start earlier and avoid paying for capacity it needs only a few hours a day.

Key figures

up to 4 months

to fulfil grid connection conditions when spare capacity exists, for sites up to 670 kW

grid connection rules, Russia

2-4 years

lead time when grid upgrades are required

grid company practice

hours, not megawatts

storage covers peak hours, not the entire load

calculation principle

Why a site waits for the grid

Capacity shortage in the node

There is no spare capacity at the substation, and the grid connection conditions require an upgrade with a long lead time.

Peaks shorter than a day

The site needs high power only a few hours a day: charging stations, equipment starts, seasonal load.

Expensive new capacity

The grid connection fee grows with capacity, and it has to be paid up front.

Business deadlines

A warehouse, plant or data center has to start now, not after the grid company finishes construction.

Solution

How it works

The storage acts as a buffer between the grid and the load: grid consumption does not exceed the allocated capacity, and the battery supplies the difference.

  1. Profile-based calculationWe determine how much power and for how many hours is missing, and size the energy and power of the storage.
  2. Charging within the limitDuring low-load hours the storage charges without exceeding the allocated capacity.
  3. Covering peaksWhen the load exceeds the limit, the storage supplies the difference. A power limiter prevents exceeding the grid capacity.
  4. After the upgradeOnce the grid is reinforced, the storage stays on site and moves to lowering capacity charges and providing backup.
Power flows with limited capacity
Grid, capacitylimit unstable Genset backup Power limiter Site Storage
  • primary source
  • backup
  • unstable
  • not available

Grid consumption does not exceed the allocated capacity.

When storage beats a capacity increase

SituationWithout storageWith storage
Peak of 2-4 hours a daypaying for capacity sized to the peakcapacity sized to the average load, the battery covers the peak
Grid upgrade of 2-4 yearsthe site waits or runs on gensetsstart-up within the allocated capacity
EV charging stationshigh capacity for short sessionson-site buffer, the grid sees a flat load
Seasonal loadcapacity sits idle most of the yearstorage works all year round lowering charges

Grid connection lead times are based on current rules and grid company practice in Russia as of 10.2026. The use of storage is agreed with the grid company under the site's connection conditions.

Projects using this solution

Data from the group's manufacturers and partners as of 10.2026. Customer names are not published.

ChinaEnterprises

Outdoor 115 kWh sodium cabinets

Equipment
2 NFPP cabinets of 115 kWh
Result
continuous outdoor operation since April 2024 and February 2025

Projects

Request

Tell us about your site

Peak and average load, hourly load profile for a year (if available), tariff and price category, site climate and the task: lower electricity costs, backup, grid connection or on-site generation. We will reply with a configuration, an indicative payback and a lead time.

Add details: name, country, file

Prefer a messenger? Write to an engineer on Telegram or WhatsApp - we reply during business hours.

Request