Data center, 80 units of 2,100 kW
- Scope
- about 168 MW of backup capacity; design, supply, installation and commissioning
- Result
- largest data center project of the partner plant
Generation
Diesel gensets 6-4,000 kVA, 48 V DC gensets, containerized power modules and hybrids with LFP and NFPP storage. Selected for the load and climate of your site, supplied and serviced in Russia, Kazakhstan and Uzbekistan.
Generation partner plant data, 10.2026. Lead times depend on project location.
Why OS Power
Most suppliers sell the genset and the battery separately. We design the whole system: the genset runs less often and at efficient load, the storage picks up load instantly, and a single control system sees everything.
LFP and NFPP storage manufactured by the group connects to the genset without third-party integrators: less fuel, fewer engine hours and site visits.
48 V sodium modules discharge at -40 °C without heating; NFPP cabinets and containers are supplied in a version matching the operating range of the model. Gensets come in insulated, heated containers.
Partner plant since 1998: 5,000+ units per year; the new plant produces 4 units of 1,000 kVA and above per day, each factory tested.
Supply, commissioning, service and spare parts in Russia, Kazakhstan and Uzbekistan; EAEU documents are issued by the group's Russian company.
Solutions
For each task - a power flow diagram, operating logic, scope of supply and real projects.
Data center backup power1-3 MVA units with data center rating, containerized power modules and fuel for 48-72 hours.Learn more
Gensets for base stations48 V DC gensets and solar hybrids: 40-60 % fuel savings.Learn more
Mines, oil and gas fields, campsContainerized units and hybrid with storage: less fuel, fewer deliveries and engine hours.Learn more
Backup for industrial facilities100-3,000 kVA units, ATS, parallel operation and synchronization.Learn more
Power before grid connectionContainerized and trailer-mounted units while waiting for the grid, then site backup.Learn more
Genset + storage hybridThe genset runs less often and at efficient load: less fuel, fewer engine hours and site visits.Learn more Selection by task
| Task | What we install | Solution |
|---|---|---|
| Backup power for Tier III/IV data centers | 1-3 MVA units with data center rating, containerized power modules, fuel for 48-72 hours | Data center backup |
| Base stations without a reliable grid | 48 V DC gensets 5-27 kW, hybrid with solar and storage | Base stations |
| Mine, oil and gas field, camp | Containerized units, hybrid with storage, fuel monitoring | Remote sites |
| Backup for plants, hospitals, water utilities | 100-3,000 kVA units, ATS, parallel operation | Industry |
| Power before grid connection | Containerized and trailer-mounted units, then transfer to backup duty | Before grid connection |
| Reduce fuel consumption and engine hours | Genset + storage + solar hybrid | Hybrid |
Product line
6-4,000 kVA, 50 and 60 Hz, with Perkins, Cummins, MTU, Mitsubishi, Weichai, Yuchai, SDEC, Yanmar engines
Learn more2.0-2.4 MW data center rating with MTU 20V4000 and Mitsubishi S16R2 engines
Learn more5-27 kW DC, 40-60 % fuel savings, service every 1,000 hours
Learn moreGenset, distribution, transformer and UPS in containers up to 3,000 kVA
Learn moreUp to 4,000 kW for on-site gas-fired generation
Learn moreFuel, engine hours, alarms and refuelling forecast; Telegram alerts
Learn moreEconomics
A genset running for hours at low load wastes fuel and wears out. With storage it runs short cycles at efficient load and then stops. The calculator compares both options for your site.
Projects
Data centers in Southeast Asia and China, thousands of units at telecom operator base stations, industrial sites. Customer names are not published.
Manufacturing
Gensets are produced by the group's partner plant in China with in-house engineering, assembly and testing.
since 1998
in the market
3 sites
manufacturing in China, about 400 employees
5,000+
units per year
66,000+
gensets and power solutions supplied
4 per day
units of 1,000 kVA and above at the new 13,000 m² plant
24 hours
factory load testing
manufacturer data, 10.2026
Service
selection by load profile, single-line diagram, fuel system, noise calculation
from stock or made to order, customs clearance and EAEU documents
installation supervision or turnkey installation, site testing
scheduled service, spare parts, remote monitoring, customer staff training
OSP-DGDiesel and gas gensets6-4,000 kVA
OSP-CI-NA-115L115 kWh sodium cabinet115 kWh
OSP-CI-LFP-261L261 kWh liquid-cooled cabinet261 kWh
OSP-CT-NA-23962.4 MWh sodium container2.4 MWh
OSP-CT-LFP-50165.0 MWh container5.0 MWh
OSP-TL-NA-48100Sodium module 48 V / 100 Ah-40 °C
OSP-DC-PWRPower distribution module6-35 kV
OSP-SCSupercapacitor storageEDLC: up to 1 million cycles Related solutions
Request
Load and load profile, operating mode (backup or primary source), climate, grid availability, noise and fuel requirements. We will reply with a configuration, lead time and proposal.